Project Description
CGC Geoservices installed geotechnical instrumentation for the construction of the Christina River Bridge in Wilmington, Delaware. The instrumentation included multiple inclinometers installed to depths of 50 feet in addition to vibrating wire piezometers installed to depths of up to 25 feet. Prior to starting the work, CGC Geoservices obtained all permits from DNREC. Because of the project’s aggressive construction timeline, multiple rigs and crews were mobilized to complete the work.